Oil's worst week since 2020 takes 16 cents off the pump

Brent's 17% weekly drop cut 16 cents off regular gas, The Children's Place filed for Chapter 11, and data-center construction hit a record $96.5 billion pace.

MONDAY, NOV 09, 2026Issue 044

We might as reasonably dispute whether it is the upper or the under blade of a pair of scissors that cuts a piece of paper, as whether value is governed by utility or cost of production.

Alfred Marshall, Principles of Economics, Book V, Chapter III, 8th edition, 1920

Energy costs are easing for households while credit stress shows up in retail. AAA's regular gas average fell to $4.01, down 16 cents in a week, after Brent dropped 17% last week. The Children's Place filed for Chapter 11 with 458 US stores. Census put data-center construction at a $96.5 billion annual pace, up 90% in a year. Watch October CPI at 8:30 a.m. ET Tuesday.

The Gauges

Three moves

Markets. Brent crude fell 17% last week, its steepest weekly drop since the start of the pandemic on LSEG data, and kept sliding overnight to $96.37 from Friday’s $98.32 settle (CNBC, CNBC). The pump is catching up. AAA’s national average for regular was $4.01 this morning, down 16 cents from a week ago and 36 cents from a month ago (AAA). A 15-gallon fill-up costs about $2.40 less than last Monday. Diesel is slower: $6.17, down 12 cents on the week and still $2.44 above a year ago, which keeps freight and heating bills high going into winter. Fair objection: regular is still 94 cents over last November. We’d say the relief lands on receipts before it lands in Tuesday’s CPI, which samples October.

Credit. The Children’s Place filed for Chapter 11 in New Jersey on Sunday and plans to sell substantially all of its assets, with bids due Dec. 9 (The Children’s Place). Stores stay open for now. Some will close, and GA Group is lined up to run store sales if no buyer keeps the business going. The chain had 458 US stores on Aug. 1, in a quarter when sales fell 18.9% to $241.8 million (SEC). Liabilities were $881.3 million against $742.3 million of assets, and controlling holder Mithaq had lent it $122.9 million. Part of this is specific to kids’ apparel, where traffic fell. Still, the holiday quarter now runs under a judge. Our guess is that landlords and vendors with pre-filing invoices to carry most of the bill, since the company asked to pay only for goods delivered after the filing.

AI power. Census put private data-center construction at a $96.5 billion annual rate in September, up from $50.7 billion a year earlier (Census). That’s a 90% jump in a year when total construction spending fell 2.7% (Census). Two columns over, construction of computer and electronics plants fell to $52.6 billion from $90.2 billion. The money moved from building chips to housing them. September is preliminary, and Census says single categories can take eight months to show a trend. We doubt a revision erases a near-doubling. Data centers now run at about a quarter of the pace of new single-family homebuilding, $403.4 billion.

What could move prices

Kalshi last traded AAA’s regular average finishing November above $4.00 at 12% as of 2:50 a.m. ET, and above $3.80 at 46% (Kalshi). Traders expect the drop to stick. The risk is supply: Polymarket US has Hormuz traffic back to normal by Dec. 31 at 10% (Polymarket US). JPMorgan estimated a global surplus of 1.4 million barrels a day in October, CNBC reported. Our view: a quick rebound in Brent would undo most of that relief before Thanksgiving driving.

The calendar

October CPI and Real Earnings print Tuesday at 8:30 a.m. ET (BLS). September rose 0.6% on the month. Economists surveyed by FactSet expect 0.24% (Morningstar), and Kalshi had 66% on more than 0.2% as of 4:56 a.m. ET. A 0.4% or a 0.1% would be news. Wednesday is Veterans Day: no BLS release and a full bond-market close (SIFMA). PPI follows Friday at 8:30.

Who pays: the electric ratepayer

Private electric power construction ran at a $146.9 billion annual rate in September, up 14% from $128.8 billion a year earlier (Census). Census doesn’t split out how much of it serves data centers. A regulated utility recovers what it spends through rates once regulators sign off, and it earns an allowed return on that plant for decades. A data center pays its own power contract. The substations and lines that connect it often go into the shared rate base, where every household in the territory carries a slice.

Net net: the racks are the tenant’s bill, and the grid behind them can end up on everyone’s.

Footnotes

The Odds

MarketVenueOddsMove
Fed hikes at the December meeting (Nov 9, 2:50 am ET)Kalshi77%+7
Two Fed hikes in 2026 (Nov 9, 2:50 am ET)Polymarket (International)76%+8
October CPI rises more than 0.2% (Nov 9, 4:56 am ET)Kalshi66%new
AAA regular gas above $4.00 on Nov 30 (Nov 9, 2:50 am ET)Kalshi12%new
Hormuz traffic back to normal by Dec 31 (Nov 9, 2:50 am ET)Polymarket US10%-1

Get the morning issue by email

Who pays, who gets paid, what it costs you. Free every weekday morning, in one short read.

One address, nothing else. Unsubscribe any time. See our privacy policy.

Live numbers between issues: rates · savings and CD rates · T-bill auctions · card rates · T-bill calculator